Identification of risks in contratc of building construction
DOI:
https://doi.org/10.15665/dem.v17i1.1563Keywords:
Administrative risk, recruitment, construction, personnel managementAbstract
This research studies the administrative risks in the contracts of the different construction activities. This is because, despite the controls for the selection of the best candidates, during the legalization, execution and liquidation of the labor contracts there are drawbacks associated with multiple factors. For this, we worked with a group of builders who recognized the risks that were in the different stages. The results of the study reveal that there is high informality in the contractors and that qualification days related to administrative and accounting aspects must be carried out, among others. Also, it is found that sometimes the formats that support the different processes within companies can be confusing for contractors.
Resumen
En esta investigación se estudian los riesgos administrativos en los contratos de las distintas actividades de construcción. Esto por cuanto, a pesar de los controles para la selección de los mejores candidatos, durante la legalización, ejecución y liquidación de los contratos de mano de obra se presentan inconvenientes asociados a múltiples factores. Para ello, se trabajó con un grupo focal de constructores quienes reconocieron los riesgos que se encontraban en las distintas etapas. Los resultados del estudio revelan que existe alta informalidad en los contratistas y que deben realizarse jornadas de cualificación relacionadas con aspectos administrativos y contables, entre otros. También, se encuentra que en ocasiones los formatos que soportan los distintos procesos al interior de las empresas pueden llegar a ser confusos para los contratistas.
Resumo
Os projetos de construção de habitação exigem a terceirização de pessoal para o desenvolvimento de diferentes atividades. Às vezes, apesar dos controles para a seleção dos melhores candidatos, durante a legalização, execução e liquidação dos contratos, há desvantagens associadas a múltiplos fatores. O objetivo deste estudo é identificar os riscos durante o ciclo de vida dos contratos nas atividades de construção. Para isso, trabalhamos com um grupo focal de construtores que reconheceu os riscos existentes em diferentes estágios. Os resultados do estudo revelam que há alta informalidade em empreiteiros e que a qualificação relacionada a aspectos administrativos e contábeis, entre outros, deve ser realizada. Além disso, descobriu-se que às vezes os formatos que suportam os diferentes processos dentro das empresas podem se tornar confusos para os contratados.
References
Ahmadi, H., Nilashi, M., & Ibrahim, O. (2015). Organizational decision to adopt hospital information system: An empirical investigation in the case of Malasyan public hospitals, 84, 166-188. doi:https://doi.org/10.1016/j.ijmedinf.2014.12.004
Ahmed, A., Kayis, B., & Amornsawadwatana, S. (2007). A review of techniques for risk management in projects. Benchmarking: An International Journal , 14(1), 22-36. doi.org/10.1108/14635770710730919
Asociación Nacional de Empresarios de Colombia (ANDI). (2015). Balance 2015 y perspectivas 2016. Bogotá: ANDI.
Comisión de Naciones Unidas para el Derecho Mercantil Internacional, C. (1988). Guía Jurídica de la CNUDMI para la redacción de contratos internacionales de construcción de obras industriales (Vol. 10). Nueva York, Estados Unidos: Publicación de Naciones Unidas. Obtenido de https://www.uncitral.org/pdf/spanish/texts/procurem/construction/lgconstr-s.pdf
Confederación Colombiana de Cámaras de Comercio. (01 de Septiembre de 2011). Impacto de la formalización empresarial en Colombia. Colección Cuadernos de Análisis Económico n°. 1, 32. Bogotá, Colombia: COMFECAMARA. Obtenido de http://www.observatoriovalle.org.co/wp-content/uploads/2013/01/cuadernodeanlisiseconmicono-1-130102151103-phpapp01.pdf
Departamento Nacional de Planeación. (3 de Abril de 2001). Política de Manejo de Riesgo Contractual del Estado para Procesos de Participación Privada en Infraestructura. Documento CONPES 3107, 28. Bogotá, Colombia: Ministerio de Hacienda y Crédito Público.
Departamento Nacional de Planeación. (2013). Manual para la identificación y cobertura del riesgo en los procesos de Contratación. Colombia Compra Eficiente, 16. Bogotá, Colombia. Obtenido de www.colombiacompra.gov.co/sites/default/.../manuales/cce_manual_riesgo_web.pdf
Departamento Administrativo Nacional de Estadística. (2016). Boletín Técnico-Cuentas trimestrales-Colombia Producto Interno Bruto (PIB). Bogotá: Dirección de Difusión, Mercadeo y Cultura Estadística.
Dlamini, S. (2011). Relationship of construction sector to economic growth. School of Construction Management and Engineering, University of Reading, UK.
Gray, C., & Larson, E. (2009). Administración de Proyectos (Cuarta ed.). Oregon, Estados Unidos: Mc Graw Hill.
Insja, D., & Sihombing, L. (Enero de 2016). Identification of factors affecting cost overrun in the construction of industrial buildings.
Malaysian Journal of Industrial Technology, 1 (1), 2462-2540.
International Electrotechnical Comission. (9 de Octubre de 2009). Risk management-Risk techniques- International Standard.
KarimiAzari, A., Mousavi, N., Mousavi, S., & Hosseini, S. (2011). Risk assessment model selection in construction industry. Experts Systems with Applications, 38 (8), 9105-9111. https://doi.org/10.1016/j.eswa.2010.12.110
Khameneha, H., Taheri, A., & Ershadia, M. (2016). Offering a framework for evaluating the performance of project risk management system. Social and Behavioral Sciences 226, 82-90. doi: 10.1016/j.sbspro.2016.06.165
Ley 1150. Diario Oficinal-Imprenta Nacional de Colombia, Bogotá, Colombia, 16 de Julio de 2007.
Ley 1429. Diario Oficial No. 47.937, Bogotá, Colombia, 29 de diciembre de 2010.
Ley 1474. Diario Oficial 48.128, Bogotá, Colombia, 12 de Julio de 2012.
Ley 57. Diario Oficial 7.019, Bogotá, Colombia, 20 de abril de 1887.
Ley 80 de 1993. Diario Oficial, Bogotá, Colombia, 28 de octubre de 1993
Mills, A. (2001). A systematic approach to risk management for construction. Structural Survey, 19(5), 245-252. https://doi.org/10.1108/02630800110412615
Mohammadi, S., & Birgonul, M. (2016). Preventing claims in green construction projects through investigating the components of contractual and legal risks. Journal of Cleaner Production, 139,1078-1084. https://doi.org/10.1016/j.jclepro.2016.08.153
Mustafa, M., & Al-Bahar , J. (Febrero de 1991). Project Risk Analytic Assessment Using the Hierarchy Process. IEEE Transactions on Engineering Management, 38(1). doi:10.1109/
Pedrosa, M. (12 de Diciembre de 2016). Panorama mundial de la construcción. Recuperado el Mayo de 2017, de http://www.construccion-pa.com/noticias/panorama-mundial-la-construccion/
Zyoud, S., & Fuchs-Hanusch, D. (2017). A bibliometric-based survey on AHP and TOPSIS techniques. Expert systems with applications, 78,158-181. http://dx.doi.org/10.1016/j.eswa.2017.02.016 0957-4174
Downloads
Published
Versions
- 2020-08-20 (3)
- 2020-08-20 (2)
- 2018-10-09 (1)
How to Cite
Issue
Section
License
Instructions for filling in the Certification of Originality and the Copyright Transfer:
Keep in mind that by pressing the "save and continue" button at the end, you are assuming all the ethical and legal commitments set forth herein. They establish the responsibilities of the legislation on intellectual property rights. For this it is assumed that whoever is carrying out the action of presenting the written work in good faith and represents himself and the other authors of the postulated article.
In this sense, the authors retain all the rights of which they are owners and authorize the free reproduction of the document sent. In the event of being necessary, they will assume, by pressing the "save and continue" button, the legal responsibility derived from the patrimonial rights which are free because of the non-payment by any procedure of the Journal.
Consequently, the author (s) represented by the person who advances the postulation of the article for evaluation and eventual publication,
I (We) declare:
1. I am (we are) the author (s) of the article {here is the name of the article placed automatically}.
2. This is an original work in accordance with the intellectual property law of Colombian copyright.
3. The content of the article of the reference has not been published and that it will not be submitted to any other means of publication in written or electronic support before knowing the decision of the Editorial Committee of Dimensión Empresarial.
4. The signer of this certification guarantees that the commitment acquired here does not infringe any third-party rights.
5. The publication authorization includes its electronic file and its adaptation, if necessary, for its incorporation in the network or in any electronic format or database, as well as attaching the necessary metadata to register the work, trademarks of water or any other security or protection system.
6. The publication authorization includes reproduction on digital media. As well as its distribution and making available through institutional archives through the Internet, distribute copies, and exhibit it in Colombia and outside the country, as well as include the article in national and international indexes.
7. The author assumes all responsibility, including compensation for damages, that could be exercised against the Universidad Autónoma del Caribe by third parties who violated their rights and interests because of the assignment.
For its part, Dimension Empresarial undertakes to respect in any case the rights of the author contained in Article 30 of Law 23 of 1982, or any after it and will make the article available to the users of the Journal so that make a legitimate use of it, as permitted by the applicable legislation, provided that its authorship is cited, commercial benefit is not obtained, and derivative works are not made.
The authors agree to accept the conditions of this intellectual property note, which will be applied to this submission when it is published in this journal.